Post: Stalled Projects Resume in Siaya

Siaya: A number of infrastructure projects under the National government that had stalled in Siaya due to funding challenges are now back on track, with contractors directed to fast-track their completion. Speaking in Usenge, Acting County Commissioner Robert Ng'etich reaffirmed the government's commitment to ensuring the projects are delivered within schedule, noting that security agencies will work closely with contractors to address any security challenges that may disrupt the works.

According to Kenya News Agency, Ng'etich made the remarks during a visit by the Government Delivery Unit secretariat to Dhogoye bridge, a key crossing point linking Siaya and Busia counties. The bridge, currently under construction, is at 40 percent completion and is expected to be finalised by April 2026. Once completed, it will provide a safe and reliable passageway for residents, traders, and travelers who have for years grappled with flooding challenges along the route rendering it impassable.

The project, which commenced in June 2021, has suffered repeated delays. Major works resumed in August 2024 after earlier stalling but ground to a halt again following delays in payments. However, during the tour, the contractor reassured the Delivery Unit secretariat that this time around, all necessary materials are already on site and no major hindrances to completion are anticipated.

He explained that the initial slow progress was due to difficult subterranean conditions, including hard rocks at the construction site, which made foundation works complex and time-consuming. "Now that the hardest phase of dealing with underground rock formations is almost behind us, we are confident that the rest of the construction will proceed more smoothly," the contractor said.

Residents of Usenge have welcomed the renewed focus on completing the Dhogoye bridge, expressing hope that it will finally put an end to perennial flooding challenges that cut off transport and trade across the two counties during rainy seasons. The government has promised continuous monitoring through the Delivery Unit to ensure accountability and timely delivery of the bridge and other stalled projects across the County such as the Bondo-Linda Road.

BII Unveils $6.7 Billion Equity Strategy for Africa in Nairobi

Nairobi:British International Investment (BII), the UK development finance institution, has announced a significant new strategy in Nairobi, focusing on investing $6.7 billion in equity across Africa from 2026 to 2031. This initiative aims to attract …

COP31 Scheduled for November 2026 in Antalya, Türkiye

Antalya:The 31st Conference of the Parties to the UN Framework Convention on Climate Change is set to take place from 9 to 20 November 2026 in Antalya, Türkiye. This global gathering aims to address the accelerating climate crisis as nations work towa…

First Simandou Mining Summit Draws Over 1,000 Delegates to Conakry

Conakry:Guinea is hosting the inaugural Simandou Mining Summit in Conakry from November 11 to 14. The event, themed “The Mining Industry A Catalyst for Economic Sovereignty,” is organized by the Simandou Strategic Committee in collaboration with the M…

Biovéa Biomass Power Plant Inaugurated in Ayébo, Ivory Coast

Ayébo:The 46 MW Biovéa Énergie biomass power plant was inaugurated in Ayébo, located in the Aboisso sub-prefecture of the Sud-Comoé region. The inauguration ceremony, held on November 5, was attended by the Minister of Mines, Petroleum and Energy, Mam…

Ethiopia’s GDP Reaches $210.7 Billion Following Rebasing

Addis Ababa:Ethiopia’s Finance Minister, Fitsum Assefa, has announced the results of the GDP rebasing with the Ethiopian fiscal year 2017 (2024/25) as the new base year. The announcement was made in Addis Ababa on November 4.

According to Africa New…